Previous Foreword to SA-2017
SA-2009 was a historic collaboration between parties representing builders and subcontractors to produce a workable and reasonably balanced document that clearly set out each party's obligations, but was able to be tailored to suit particular requirements. Mark Holland of Hazelton Law should be commended for his excellent legal advice and central role in drafting the amendments for SA-2017.
Mark Holland of Hazelton Law should be recognised for his excellent legal advice and drafting of the amendments to the contract.
SA-2017 is an update to ensure compliance with the Construction Contracts Amendment Act 2015, to align the document with NZS 3910:2013 and to provide an option to enable use with NZS 3916:2013.
Following consultation with various parties from each side, changes other than those noted above were minor.
SA-2017 is only available as a PDF file. This document is subject to copyright. It may only be used without alteration.
Previous Foreword to SA-2009
A good working relationship between the Contractor and Subcontractor is critical to ensuring construction projects run smoothly and are completed on time and to budget. As much as these good relationships do exist, there has also been a long history of disputes and other problems.
This Subcontract Agreement is aimed at enhancing already established practices by ensuring obligations and responsibilities are identified up front, thereby avoiding later disputes which can be costly in both time and goodwill.
The Agreement was developed by a working group of representatives from the Registered Master Builders Federation and the New Zealand Specialist Trade Contractors Federation Incorporated (formerly the New Zealand Building Subcontractors Federation).
| Robert Finley - Hawkins Construction | Ian Butturini - Electrical Contractors Association of New Zealand |
| John Hale - Fletcher Construction | Rod Fulford - Precast New Zealand |
| Noel O'Rourke - Mainzeal Construction | Roger O'Neil - Reinforcing New Zealand Incorporated |
| Tim Strawbridge - Foster Construction | Mike Sentch - Roofing Association New Zealand Incorporated |
| Legal advice provided by: Michael Weatherall - Simpson Grierson | Project Managers: Rob Steele |
| Mary Haggie - Kensington Swan | Grant Thomas |
| Andrew Hazelton - Hazelton Law | |
The document has four parts:
1. The Subcontract Agreement.
2. The Subcontract Specific Conditions (which includes Special Conditions).
3. The Subcontract General Conditions.
4. Appendices.
The Subcontract Agreement contains basic information naming the parties, price, etc, and lists the subcontract documents.
The Subcontract General Conditions make up the bulk of the document and contain the standard contract clauses that should not be changed. Attempts to tailor the Subcontract General Conditions are likely to mislead parties and result in confusion or disputes. If any changes to these conditions are required by either party or the particular head contract, they must be covered in the Subcontract Specific Conditions.